Fungsinya

Skill ini menulis pembaruan status singkat untuk sebuah proyek agar pihak berkepentingan bisa memahaminya tanpa membuka isu apa pun. Cocok untuk pemimpin proyek yang melaporkan kemajuan kepada orang lain.

Kapan dipakai

  • โœ“Saat seseorang meminta pembaruan proyek atau postingan status untuk pihak berkepentingan.
  • โœ“Saat Anda perlu mengatakan dengan jujur apakah sebuah proyek akan selesai tepat waktu.
  • โœ“Saat Anda ingin menyebutkan risiko dan satu keputusan yang perlu diambil.

Link skill

https://github.com/ParadevAI/Paradev/blob/main/plugins/linear/skills/project-status/SKILL.md

Salin lalu tempelkan ke AI Anda (Claude, ChatGPT, atau Cursor) dan minta AI mengikuti instruksinya.

Cara pakai

Cara paling mudah: salin pesan ini dan tempelkan ke AI Anda. AI akan membaca skill dan mengikuti instruksinya.

Pesan siap tempel

Gunakan skill ini untuk membantu saya: https://github.com/ParadevAI/Paradev/blob/main/plugins/linear/skills/project-status/SKILL.md Baca file SKILL.md di link tersebut dan ikuti instruksinya untuk tugas saya.
Mau AI Anda menemukan skill seperti ini sendiri?Pasang MCP Skillpedia gratis: cukup satu baris, dan AI mencari di antara 15.000+ skill sebelum tiap tugas.Pasang dalam 1 menit โ†’

Contoh permintaan ke AI

โ€œSusun pembaruan status minggu ini untuk proyek Atlas, termasuk apakah proyeknya berjalan sesuai jadwal.โ€

5 skill baru setiap minggu. 1 menit baca.

Cara kerjanya

Agent membandingkan isu proyek dengan pembaruan sebelumnya untuk melihat apa yang bergerak, bukan mengandalkan persentase selesai. Lalu ia membuat penilaian yang jelas, yaitu sesuai jadwal, berisiko, atau melenceng, dan menyebut risiko sebagai kejadian yang mungkin terjadi.

Konten teknis (SKILL.md asli)

Teks asli dari pembuat, dalam bahasa Inggris, langsung dari GitHub.

Draft a project status update

A status update is read by people who will not open a single issue. It has to survive being the only thing they read: is this landing, what changed, and what do you need from them.

1. Read the movement, not the snapshot

Percent-complete is the number people reach for and the one that lies. A project can sit at 70% for a month while the last three issues get harder. What tells the story is what moved since the previous update: issues completed, issues added, and target dates that shifted.

Fetch the project's issues plus its previous status update. Without the previous one you are writing a summary, not an update, and the reader cannot tell what is new.

2. Judge the trajectory honestly

Pick one and commit to it. Hedging every sentence is how a project stays green until the week it ships late.

Call What justifies it
On track Remaining scope fits the remaining time at the current rate
At risk A dependency, an unknown, or a rate that has to improve to land
Off track The date will move, or scope has to be cut โ€” say which

If you cannot tell, the answer is at risk, and the reason is that nobody can tell.

3. Name risks as things that could happen

"Backend integration is risky" gives the reader nothing. "The export endpoint is not built, we cannot finish import until it is, and the owner is on the payments migration until the 14th" tells them what to move. A risk is a specific event with a specific consequence and usually a specific person who can prevent it.

Include scope that was added mid-project. Silently absorbed scope is why the date moves, and it is invisible unless the update names it.

4. Ask for what you need

Most updates end with nothing to do, so nothing is done. If a decision, a person, or a descope would help, state it as the last line with a name and a date attached. One ask is better than three, because three get triaged and one gets answered.

5. Show the draft, then post it

Print the draft in full and stop. This skill drafts; publishing is the user's call. A status update is read by stakeholders and enters the project's permanent history, and a wrong trajectory or a risk named for the wrong person is not something a follow-up correction undoes โ€” so an unreviewed post is worse than a late one.

Once they approve it, write it on the project so it lives next to the work rather than in a chat message that is gone by the next morning. Keep it to a few short paragraphs: trajectory, what moved, risks, the ask. If they asked only for a draft, stop after printing it.

Anti-patterns

  • Listing every completed issue. That is the changelog, not the update.
  • "No blockers" when the real answer is that nobody has looked. Say you have not looked.
  • Copying the previous update with the numbers changed. The reader learns to skip it, and the one update that matters gets skipped too.
Pertanyaan umum

Mengapa tidak melaporkan persentase selesai saja?

Persentase selesai bisa tetap sama sementara pekerjaan yang tersisa menjadi lebih sulit, jadi skill ini melihat apa yang bergerak sejak pembaruan terakhir.

Bagaimana jika statusnya belum jelas?

Skill ini menyatakan berisiko dan memberikan alasannya, karena belum ada yang bisa memastikan proyek akan selesai.

Apakah ia menghindari kata-kata yang samar?

Ya. Ia meminta agar risiko disebut sebagai kejadian spesifik, bukan kekhawatiran umum.

Detail

Deskripsi asli dari pembuat

Draft a Linear project status update from what actually moved โ€” progress, risks, and the one decision that needs making. Use when someone asks for a project update, a status post, where a project stands, whether it will land on time, or what to tell stakeholders.

repo: ParadevAI/Paradev

Popularitas

Bintang GitHub
16k
Peringkat
#10834
Lisensi
โ€”
Diperbarui
2/11/2026

Apakah skill ini berguna?

0

Masuk untuk memberi suara.

Komentar

  • โ€ฆ

Skill lain dari repositori ini

Skill serupa