project-status

O que ela faz

Esta skill escreve uma atualização curta de status para um projeto, para que as partes interessadas entendam a situação sem abrir nenhuma issue. É para líderes de projeto que reportam progresso a outras pessoas.

Quando usar

  • ✓Quando alguém pede uma atualização de projeto ou um post de status para as partes interessadas.
  • ✓Quando você precisa dizer honestamente se um projeto vai terminar no prazo.
  • ✓Quando você quer nomear os riscos e a única decisão que precisa ser tomada.

Link da skill

https://github.com/ParadevAI/Paradev/blob/main/plugins/linear/skills/project-status/SKILL.md

Copie e cole na sua IA (Claude, ChatGPT ou Cursor) pedindo para seguir as instruções.

Como usar

O jeito mais fácil: copie a mensagem e cole na sua IA. Ela lê a skill e segue as instruções.

Mensagem pronta para colar

Use esta skill para me ajudar: https://github.com/ParadevAI/Paradev/blob/main/plugins/linear/skills/project-status/SKILL.md Leia o arquivo SKILL.md desse link e siga as instruções dele na minha tarefa.
Quer que a sua IA encontre skills como esta sozinha?Instale o MCP grátis do Skillpedia: uma linha, e ela pesquisa entre 15.000+ skills antes de cada tarefa.Instalar em 1 minuto →

Exemplo do que pedir para a IA

“Redija a atualização de status desta semana do projeto Atlas, incluindo se ele está no prazo.”

5 skills novas por semana. 1 minuto de leitura.

Como funciona

O agente compara as issues do projeto com a atualização anterior para ver o que avançou, em vez de depender do percentual concluído. Depois dá um veredito claro, no prazo, em risco ou fora do prazo, e nomeia os riscos como eventos que podem acontecer.

Conteúdo técnico (SKILL.md original)

Texto original do autor, em inglês, direto do GitHub.

Draft a project status update

A status update is read by people who will not open a single issue. It has to survive being the only thing they read: is this landing, what changed, and what do you need from them.

1. Read the movement, not the snapshot

Percent-complete is the number people reach for and the one that lies. A project can sit at 70% for a month while the last three issues get harder. What tells the story is what moved since the previous update: issues completed, issues added, and target dates that shifted.

Fetch the project's issues plus its previous status update. Without the previous one you are writing a summary, not an update, and the reader cannot tell what is new.

2. Judge the trajectory honestly

Pick one and commit to it. Hedging every sentence is how a project stays green until the week it ships late.

Call What justifies it
On track Remaining scope fits the remaining time at the current rate
At risk A dependency, an unknown, or a rate that has to improve to land
Off track The date will move, or scope has to be cut — say which

If you cannot tell, the answer is at risk, and the reason is that nobody can tell.

3. Name risks as things that could happen

"Backend integration is risky" gives the reader nothing. "The export endpoint is not built, we cannot finish import until it is, and the owner is on the payments migration until the 14th" tells them what to move. A risk is a specific event with a specific consequence and usually a specific person who can prevent it.

Include scope that was added mid-project. Silently absorbed scope is why the date moves, and it is invisible unless the update names it.

4. Ask for what you need

Most updates end with nothing to do, so nothing is done. If a decision, a person, or a descope would help, state it as the last line with a name and a date attached. One ask is better than three, because three get triaged and one gets answered.

5. Show the draft, then post it

Print the draft in full and stop. This skill drafts; publishing is the user's call. A status update is read by stakeholders and enters the project's permanent history, and a wrong trajectory or a risk named for the wrong person is not something a follow-up correction undoes — so an unreviewed post is worse than a late one.

Once they approve it, write it on the project so it lives next to the work rather than in a chat message that is gone by the next morning. Keep it to a few short paragraphs: trajectory, what moved, risks, the ask. If they asked only for a draft, stop after printing it.

Anti-patterns

  • Listing every completed issue. That is the changelog, not the update.
  • "No blockers" when the real answer is that nobody has looked. Say you have not looked.
  • Copying the previous update with the numbers changed. The reader learns to skip it, and the one update that matters gets skipped too.
Perguntas frequentes

Por que não reportar apenas o percentual concluído?

O percentual pode continuar igual enquanto o trabalho restante fica mais difícil, então a skill olha o que avançou desde a última atualização.

E se o status não estiver claro?

A skill diz em risco e dá o motivo, já que ninguém consegue saber ainda se o projeto vai terminar.

Ela evita linguagem vaga?

Sim. Ela pede ao agente que nomeie os riscos como eventos específicos, e não como preocupações gerais.

Detalhes

Descrição original do autor

Draft a Linear project status update from what actually moved — progress, risks, and the one decision that needs making. Use when someone asks for a project update, a status post, where a project stands, whether it will land on time, or what to tell stakeholders.

repo: ParadevAI/Paradev

Popularidade

Estrelas no GitHub
16 mil
Posição no ranking
#10834
Licença
—
Atualizada em
02/11/2026

Essa skill é útil?

0

Entre para votar.

Comentários

  • …

Mais skills deste repositório

Skills parecidas